Lauchernalp, November 2026 | Core and shell complete | Dear Tourmaline and Lauchernalp Resort family, |
|
|
We have reached a major milestone: the core and shell of Tourmaline is officially complete. All concrete work, services and service shafts, internal and external walls, the full roof and every window are now installed. Our teams at Zengaffinen and Renggli have done an incredible job to get us here. |
|
Building at 2,000 m in the Swiss Alps, you move at the mountain's pace – and with early snowfall and a sharp drop in temperature, the mountain set the pace this autumn. Renggli will formally hand over the core and shell on Friday, 20 November. |
|
|
Tourmaline · Core and shell | Officially complete | Handover by Renggli · 20 November 2026 |  | Front elevation, architect's drawing | ✓ | All concrete work | ✓ | Services and service shafts | ✓ | Internal and external walls |
|
|
✓ | The full roof | ✓ | Every window |
| NEXT The underfloor heating |
|
|
|
|
Progress · June to November 2026 | From foundations to roof |
|
|
|
The next phase | Why the programme has moved |
|
|
With the building closed, the teams can now work inside. I want to be open with you about what that means for the programme. | Our goal was to hand over the units in December. That will not be possible. The next phase is the underfloor heating, which requires a concrete screed that cannot be poured below 5°C. |
|
 | Inside Tourmaline, November 2026 |
|
|
There are chemical additives that allow pouring in colder conditions, but we are delivering a premium asset and we need to guarantee the building to the highest standard. As principals of Lauchernalp Resort, we have decided not to take that risk. The knock-on effect is that the kitchens, bathrooms, flooring and furniture cannot go in until the screed is down. Our interior partner has already started manufacturing – all designs are signed off and the order is placed – so once the building is ready, the fit-out will move quickly. |
|
|
 |
“Where we have had to choose, we have chosen quality over speed, every time.Toni Enderli |
Revised programme | The road to key handover |
|
|
20 Nov 2026 Core and shell | Jul – Aug 2027 Key handover | Dec 2027 Clubhouse open |
|
| 20 November 2026 | | Core and shell complete, handover by Renggli COMPLETE | | December 2026 | | Road closed for the season since 18 November. All painting, electrical, heating and plastering materials are already on site. Electrical, plumbing and heating installation proceeds. | | January 2027 | | Work continues inside on the electrical installation. | | February 2027 | | Plastering and painting completed. | | April 2027 | | Installation of coatings. | | Mid-May 2027 | | Road reopens. Baur Interior begins the full fit-out: flooring, cupboards, kitchens, bathrooms and all furniture. | End July – 14 August 2027 | | Key handover. | | December 2027 | | Clubhouse open and operational, ready for the ski season. |
Complete Upcoming Road closed for the season |
|
|
All focus is on Tourmaline; the Clubhouse follows. Renggli will build the Clubhouse's top structure, all planning and designs have been handed over, and the Clubhouse will open and be operational in December 2027, ready for the ski season. |
|
|
One further decision | CHF 2 million | Connecting tunnels between Tourmaline and the Clubhouse |
|
|
|
One further decision I want to share. We have committed CHF 2 million to connecting tunnels between the buildings, Tourmaline and the Clubhouse. This was a major investment and not an easy call, but it transforms the guest experience – and a better experience means higher occupancy, stronger returns and added capital growth for every owner. |
|
|
 |
Visualisation: Tourmaline in winter, once complete. |
|
|
I hope you understand that we and our teams have given everything to reach the original milestones. Where we have had to choose, we have chosen quality over speed, every time. The capital growth across each property type has already increased substantially, and will do so again once the resort is fully operational. |
|
We will continue to send you regular updates through the winter and into 2027 as each phase completes. Every owner will receive at least 30 days' written notice of their key handover date, so you can plan your first visit with certainty. |
|
|
Thank you for your trust, patience and support. We value it enormously, and I am comfortable that through the Building Lauchernalp channel you have been with us every step of the way. |
|
|
 | Warm regards, Toni EnderliFor the principals of Lauchernalp Resort Lauchernalp Resort AG |
|
|
|
 |
A personal invitation | Come and see your view this winter |
|
|
The handover date has moved, but the view has not. If you would like to visit Tourmaline this winter, I would be delighted to host you personally. We will step out onto your balcony, raise a glass of champagne to the view that will soon be yours, and then enjoy a good lunch together on the mountain. |
|
These visits are one on one and by appointment, as Tourmaline is still an active site. Simply reply to this email or message me directly, and we will find a date that suits you. | | ARRANGE YOUR VISIT |
|
|
|
|
|